“At the tender of the Directorate of Public Works for the construction of a football (soccer) stadium in Cetinje, the decision of choosing the company called Erlang is the only correct one. There have been no appeals so there is no interference to the construction contract that will be signed during the next week for works to start before the local elections on November 26th, learned Vijesti.

The construction of the stadium with a capacity of 5,192 sets has been announced for years. The tender was published on August 25, and then five times in exchange and clarified twice. The deadline for bid submissions was until 9 o’clock on October 13, and all three bids were submitted in the last 20 minutes. The evaluation of bids was completed in only 10 days with no complaints, and the construction of the foundation can begin before the election.” (translated from Vijesti)